The Luxembourg Roads Administration will carry out construction works on the A13 motorway from Tuesday 26 March until late-July 2019.

Works related to the restoration of the OA 1073 art work will begin next Tuesday on the A13 motorway between the Dudelange-Burange bypass and the Croix de Bettembourg. This will be the first of four construction phases. The works include the support of the structure for the purpose of reducing the size in order to build the future cycle lane between Dudelange-Burange and "Krakelshaff".

The planned duration of the construction for the four phases is approximately four months and extends until the end of July 2019. The first phase of the project includes the stripping of the existing corniche, the installation of a restraint system and the renewal of the waterproofing of the roadway. During this period, the A13 hard shoulder, in the vicinity of the construction site, will be blocked off to traffic in both directions between the Dudelange-Burange bypass and the Croix de Bettembourg.